Project Dashboard
Real-time overview of Casa Frangipani · Nagaon, Alibag
Budget
₹3.5 Cr
Spent: ₹2.2 Cr
Progress
62%
3/12 components done
Components
12
6 active · 1 issues
Cost Variance
-50.1%
Under budget
Phase Timeline
✓
Design & Planning100%
✓
BOQ & Procurement100%
✓
Civil Work100%
4
Execution62%
5
Finishing10%
6
Handover0%
Component Status Breakdown
Completed3
In Progress6
Pending2
Issues1
Kitchen backsplash grout shade inconsistency detected
Carpentry delay risk: 6 day slippage projected